1) Preliminary Preparations
After the high-pressure blower is installed, the cooling water flow rate, pressure, and temperature must be checked. The lubricating oil level and whether the inlet and outlet valves of the high-pressure blower duct system are open must also be checked. Before starting the high-pressure blower, it is essential to confirm that the above checks are satisfactory and to disengage the interlock system.
2) Starting the Blower Unit
Upon receiving the blower unit start command, the on-site operator must check that the starting current is within the normal range and gradually open the blower inlet valve, observing the current indicator. Stop opening the valve when the rated current reaches 90% or more. The blower will then be operating in a venting state, ready to supply air to the aeration tank. When the electric air supply valve is opened, the air supply resistance of the blower will decrease. If the resistance decreases to a certain extent, blower surging may occur. Therefore, the venting valve must be opened gradually; opening it completely at once is strictly prohibited.